Car park resurfacing in Paraburdoo

Published on Monday, 20 February 2017 at 12:00:00 AM

The Shire of Ashburton intends to carry out car park resurfacing works in the car park behind IGA, Fortescue Place and Anzac Ave, Paraburdoo.

The proposed works consist of preparation of the existing surface ready for the application of a 2 coat seal, ATM asphalt has been contracted to carry out the work.

The works are expected to be completed in 5 days.

The first 2 days, which involves cleaning and preparing of the existing road surface, is programmed to occur on Tuesday 21st of February, between the hours of 7am and 5pm. Access to properties will be possible for the duration of the shift and traffic control personnel will be present at all times.

The second shift, which involves placing and finishing a new 2 coat seal surface, is programmed to occur on from Thursday the 23rd until Saturday the 25th, between the hours of 7am and 5pm. Access to properties will be possible for the duration of the shift and traffic control personnel will be present at all times.

We apologise for any inconvenience these works may cause. Your co-operation is appreciated.

If you require any further information regarding these works please contact the Shire's representative, Shane Godfrey on 08 9188 4459