Notice of intention to carry out concrete works
Published on Monday, 22 May 2017 at 12:00:00 AM
The Shire of Ashburton intends to carry out concrete civil works in Tom Price, Paraburdoo and Onslow. The proposed works consist of installation of new footpaths, the renewal of existing footpaths and the renewal of kerb and channel.
Dowsing Group has been contracted to carry out the work and the works are expected to take 8 weeks to complete.
The project is scheduled to commence on the 29/05/2017 with the contractor establishing traffic management, utility Iocations, demolition work and concreting. Access to certain properties may be restricted for brief periods during working hours. Arrangements will be made with affected business/property owners prior to any such restrictions being implemented. Traffic control personnel will be present during working hours. Below are the Iocations of works in each town:
The expected completion date for the project is the 28/07/2017
We apologise for any inconvenience these works may cause. Your co-operation is appreciated.
If you require any further information regarding these works please contact the Shire's representative, Shane Godfrey on 08 9188 4459.